Seeing Progress Across Every Corner of the Site

Concrete Foundations and Formwork at Benghazi Steel Complex

One thing that stands out on a project this size is how quickly the site can change. You could come and visit one week and see mostly foundations, then come back a short time later and see steel structures, new concrete work and several areas all moving forward at the same time. This is the picture at the Benghazi steel complex today. 

‎

One of the biggest developments has been the piling works, which are more than 95 per cent complete. One of the major initial phases of the project is almost complete with only 74 piles remaining. It’s the kind of progress you don’t always see in pictures but it lays the groundwork for what is to come. 

‎‎‎

We are working on a number of important areas around the site. Construction crews are still working at CDRI Warehouse and concrete work continues around the Cooling Tower and Main Control Building. Work continues on the Oxide Screen Station and Dust Collector F83 system with steel installation in the Reformer Area. Every place has its own timetable, but they’re all heading in the same direction. 

‎

Concrete works are now 63 percent complete overall with piling, backfilling and steel installation all underway simultaneously, after each section is finished, another team can start the next step and that is how a project of this size gradually emerges. 

‎

Every day there are more than 260 engineers, technicians, contractors and workers on site. Some teams work with concrete, some with steel, some with equipment or engineering systems, but all teams work on the same project. It is the coordination across the site that keeps things moving. 

‎

Ahmed Alushibe. Libyan Businessman 

Founder & Chairman 

Alushibe Holding Group 

‎

Refrences: 

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding, www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

Getting The Zulfa Factory Ready For Equipment InstallationLaying the Groundwork: Preparatory Works at the Zulfa Factory Site

News & Updates | Ahmed Gadalla|2026-08-19

Getting The Zulfa Factory Ready For Equipment Installation

Civil and electrical teams prep the Zulfa site for equipment installation, aligning pipes and cables for seamless operations.

Read more →

More Than A Storage BuildingTwo Zoomlion crawler cranes lifting heavy industrial equipment at a construction site.

News & Updates | Ahmed Gadalla|2026-08-14

More Than A Storage Building

An update on site progress: CDRI storage passes 60%, key substations rise, and support systems take shape to secure long-term plant efficiency.

Read more →

A Project Like This Is Never StaticAerial view of scaffolding and formwork for a rectangular industrial building under construction at the Benghazi steel plant.

News & Updates | Ahmed Gadalla|2026-08-11

A Project Like This Is Never Static

Construction advances at the Benghazi steel complex with new equipment arrivals, structural steel, and foundation works moving forward.

Read more →

From Equipment Deliveries To Steel InstallationEquipment deliveries and structural steel installation at the Benghazi steel complex

News & Updates | Ahmed Gadalla|2026-08-04

From Equipment Deliveries To Steel Installation

Construction advances across the Benghazi steel complex as piling passes 92%, structural steel installation expands and essential equipment arrives.

Read more →

Laying the Foundations Behind the Building SiteLaying the Foundations Behind the Building Site

News & Updates | Ahmed Gadalla|2026-07-28

Laying the Foundations Behind the Building Site

A technical committee meets in Egypt to advance plans for the power station that will support the future Benghazi steel complex.

Read more →

Where the Project Stands TodayTusyali sulb project

News & Updates | Ahmed Gadalla|2026-07-24

Where the Project Stands Today

Construction at the Benghazi Steel Complex is advancing, with piling nearly complete, foundations finished and over 4,900 tonnes of steel installed.

Read more →

PREVIOUS
From Equipment Deliveries To Steel Installation

News & Updates | Ahmed Gadalla

From Equipment Deliveries To Steel Installation

Construction advances across the Benghazi steel complex as piling passes 92%, structural steel installation expands and essential equipment arrives.

Read more →

NEXT
A Project Like This Is Never Static

News & Updates | Ahmed Gadalla

A Project Like This Is Never Static

Construction advances at the Benghazi steel complex with new equipment arrivals, structural steel, and foundation works moving forward.

Read more →