A Project Like This Is Never Static

Aerial view of scaffolding and formwork for a rectangular industrial building under construction at the Benghazi steel plant.

With a project of this size, one of the things is there’s always something going on. One team is finishing up concrete work, another is putting up steel, and elsewhere new equipment is coming in to get ready for the next phase. That is precisely what has been happening at the Benghazi steel complex lately.

‎

One of the newest arrivals is the Top Gas Scrubber, an important piece of equipment to be incorporated into the reduction furnace of the plant. Once in place it will cool and clean the process gases before they are reused in production, improving the plant’s efficiency. It took a lot of planning to bring equipment of this size to site and its arrival is another step forward for the project.

‎

But that’s not the end of the job. Construction teams continue to make progress on the future 220 kV substation, including work to prepare foundations for the electrical systems that will power the complex in the future. Oxygen tanks have also been delivered and work on the utility systems and other construction activities continues.

‎

Elsewhere on the site, different aspects of the project continue to advance together. The Reduction Area, the Reformer Area and the Gas Compressor Building are now seeing structural steel constructed, while piling and concrete works are still taking place in the vicinity of the Cooling Tower. Work continues on the masonry of the services building with each team concentrating on a different area of the overall development.

‎

Concrete works, backfilling and structural steel installation are all continuing to move forward with the latest progress figures showing steady movement across the project. Those updates are important because they show that progress isn’t just happening in one area of the site. The project is progressing steadily with different parts being developed simultaneously.

‎

Today, looking across the Benghazi steel complex, each stage clearly supports the next. Whether it's a new equipment delivery, another foundation completed or steel going up on site, each step contributes to the bigger picture. The project is taking shape bit by bit and it is a pleasure to see that the progress is becoming more and more visible with every update.

‎

Ahmed Alushibe. Libyan Businessman

Founder & Chairman

Alushibe Holding Group

‎

References:

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding,

www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

Getting The Zulfa Factory Ready For Equipment InstallationLaying the Groundwork: Preparatory Works at the Zulfa Factory Site

News & Updates | Ahmed Gadalla|2026-08-19

Getting The Zulfa Factory Ready For Equipment Installation

Civil and electrical teams prep the Zulfa site for equipment installation, aligning pipes and cables for seamless operations.

Read more →

More Than A Storage BuildingTwo Zoomlion crawler cranes lifting heavy industrial equipment at a construction site.

News & Updates | Ahmed Gadalla|2026-08-14

More Than A Storage Building

An update on site progress: CDRI storage passes 60%, key substations rise, and support systems take shape to secure long-term plant efficiency.

Read more →

Seeing Progress Across Every Corner of the SiteConcrete Foundations and Formwork at Benghazi Steel Complex

News & Updates | Ahmed Gadalla|2026-08-07

Seeing Progress Across Every Corner of the Site

Progress continues at the Benghazi steel complex as piling works near completion and concrete structures take shape.

Read more →

From Equipment Deliveries To Steel InstallationEquipment deliveries and structural steel installation at the Benghazi steel complex

News & Updates | Ahmed Gadalla|2026-08-04

From Equipment Deliveries To Steel Installation

Construction advances across the Benghazi steel complex as piling passes 92%, structural steel installation expands and essential equipment arrives.

Read more →

Laying the Foundations Behind the Building SiteLaying the Foundations Behind the Building Site

News & Updates | Ahmed Gadalla|2026-07-28

Laying the Foundations Behind the Building Site

A technical committee meets in Egypt to advance plans for the power station that will support the future Benghazi steel complex.

Read more →

Where the Project Stands TodayTusyali sulb project

News & Updates | Ahmed Gadalla|2026-07-24

Where the Project Stands Today

Construction at the Benghazi Steel Complex is advancing, with piling nearly complete, foundations finished and over 4,900 tonnes of steel installed.

Read more →

PREVIOUS
Seeing Progress Across Every Corner of the Site

News & Updates | Ahmed Gadalla

Seeing Progress Across Every Corner of the Site

Progress continues at the Benghazi steel complex as piling works near completion and concrete structures take shape.

Read more →

NEXT
More Than A Storage Building

News & Updates | Ahmed Gadalla

More Than A Storage Building

An update on site progress: CDRI storage passes 60%, key substations rise, and support systems take shape to secure long-term plant efficiency.

Read more →