Getting The Zulfa Factory Ready For Equipment Installation

Laying the Groundwork: Preparatory Works at the Zulfa Factory Site

On a construction site, the buildings and structures are the most obvious signs of progress, of course. But behind them is a lot of planning that needs to happen before each new stage can start. 

‎

This is what is happening at the Zulfa Food Industries project at the moment. Construction continues across the site and engineers and project teams are already preparing for the installation of equipment. A lot to work through before the machinery comes. Everything has to be planned so that when the time comes, all the pipes, all the cables and all the connections fit properly together. 

‎

Zulfa’s management team, engineers, consultants and contractors met recently with representatives from Tetra Pak Egypt and SIA Solutions at the factory to help move that work forward. Together they walked the site, took stock of progress and discussed what still needs to be done before equipment can start to be installed. 

‎

There was a lot of talk about practicalities. The teams checked piping systems, drainage, insulation, electrical cable routes and the position of future equipment and storage tanks. These are not the things that are obvious in a photograph but decisions that make the whole factory work more efficiently once production is underway. 

‎

Civil, mechanical, electrical and piping teams are working all over the site, co-ordinating their activities from day to day. Everyone has their own job, but we’re all working toward the same goal, which is getting the factory ready for what’s next. 

‎

When I look at the project today I see more than buildings going up. But I see a lot of careful planning going on at the same time. 

‎

Ahmed Alushibe. Libyan Businessman

Founder & Chairman

Alushibe Holding Group 

‎

References: 

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding, www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

More Than A Storage BuildingTwo Zoomlion crawler cranes lifting heavy industrial equipment at a construction site.

News & Updates | Ahmed Gadalla|2026-08-14

More Than A Storage Building

An update on site progress: CDRI storage passes 60%, key substations rise, and support systems take shape to secure long-term plant efficiency.

Read more →

A Project Like This Is Never StaticAerial view of scaffolding and formwork for a rectangular industrial building under construction at the Benghazi steel plant.

News & Updates | Ahmed Gadalla|2026-08-11

A Project Like This Is Never Static

Construction advances at the Benghazi steel complex with new equipment arrivals, structural steel, and foundation works moving forward.

Read more →

Seeing Progress Across Every Corner of the SiteConcrete Foundations and Formwork at Benghazi Steel Complex

News & Updates | Ahmed Gadalla|2026-08-07

Seeing Progress Across Every Corner of the Site

Progress continues at the Benghazi steel complex as piling works near completion and concrete structures take shape.

Read more →

From Equipment Deliveries To Steel InstallationEquipment deliveries and structural steel installation at the Benghazi steel complex

News & Updates | Ahmed Gadalla|2026-08-04

From Equipment Deliveries To Steel Installation

Construction advances across the Benghazi steel complex as piling passes 92%, structural steel installation expands and essential equipment arrives.

Read more →

Laying the Foundations Behind the Building SiteLaying the Foundations Behind the Building Site

News & Updates | Ahmed Gadalla|2026-07-28

Laying the Foundations Behind the Building Site

A technical committee meets in Egypt to advance plans for the power station that will support the future Benghazi steel complex.

Read more →

Where the Project Stands TodayTusyali sulb project

News & Updates | Ahmed Gadalla|2026-07-24

Where the Project Stands Today

Construction at the Benghazi Steel Complex is advancing, with piling nearly complete, foundations finished and over 4,900 tonnes of steel installed.

Read more →

PREVIOUS
More Than A Storage Building

News & Updates | Ahmed Gadalla

More Than A Storage Building

An update on site progress: CDRI storage passes 60%, key substations rise, and support systems take shape to secure long-term plant efficiency.

Read more →